Upgrade existing watermain on Mary Street to 300mmm diameter line
Federal contribution
$273,249
Federal share17%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Petawawa
- Construction start
- Jul 5, 2017(actual)
- Construction end
- Jun 7, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2017
- Construction end8 weeks earlyforecast Jul 31, 2018
Also in Petawawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49087 in the federal list. How to read these figures.