Rehabilitation of Municipal Building
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Baldwin
- Construction start
- Dec 20, 2021(actual)
- Construction end
- Aug 4, 2022(actual)
Against the original forecast
- Construction end2 months lateforecast May 31, 2022
Also in Baldwin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59387 in the federal list. How to read these figures.