Slope Excavation, Application of Geosynthetic Clay Liner, Regrading of the Failing Berm as well as required Engineering at the Baldwin Township Exfiltrating Lagoon
Federal contribution
$50,000
Federal share48%
of $104.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Baldwin
- Construction start
- Oct 31, 2017(actual)
- Construction end
- Dec 31, 2017(actual)
Against the original forecast
- Construction start6 months lateforecast May 15, 2017
- Construction end4 weeks lateforecast Dec 1, 2017
Also in Baldwin