Municipal trail system upgrades and installations
Federal contribution
$46,018
Federal share80%
of $57.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Springwater
- Construction start
- Sep 20, 2021(actual)
- Construction end
- Nov 10, 2023(actual)
Against the original forecast
- Construction end7 weeks earlyforecast Dec 30, 2023
Also in Springwater
- Installation of Mechanical Ventilation; Ventilation Improvement; Portable Unit Ventilator; Portable Replacement; Portable Refurbishment$7.7M
- Ventilation Improvement; Sanitizing Station$3.0M
- Improvements to Highway 400 Detour Routes - Wilson Drive$816.7K
- Bottle Filling Stations; Touchless Door Open Devices$575.0K
- Queen Street East$437.4K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59421 in the federal list. How to read these figures.