Back to projects

Roof Top Unit (RTU) Replacement

Guelph, Ontario

completeHealthcare InfrastructureCVRIS
Federal contribution
$1.5M
$1,492,536
Federal share80%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
202220232024
Built

Approved 3 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 1, 2022(actual)
Construction end
Dec 31, 2023(actual)

Also in Guelph