AR Goudie NFP LTC Retrofit, Repairs, Upgrades

Kitchener, Ontario

completeVentilationCVRIS
Federal contribution
$4.6M
$4,596,565
Federal share80%

of $5.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
202220232024
Built

Approved 3 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 1, 2021(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jan 1, 2022

Also in Kitchener

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59467 in the federal list. How to read these figures.