Back to projects

St. Joseph's Villa of Sudbury Long-Term Care Home HVAC Upgrade

Greater Sudbury, Ontario

completeVentilationCVRIS
Federal contribution
$1.4M
$1,412,621
Federal share80%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
202220232024
Built

Approved 3 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 4, 2022(actual)
Construction end
Dec 22, 2023(actual)

Against the original forecast

  • Construction start9 months lateforecast Jul 15, 2021
  • Construction end13 months lateforecast Nov 30, 2022

Also in Greater Sudbury