HVAC Upgrades
Federal contribution
$136,000
Federal share80%
of $170.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
202220232024
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Regional Municipality of Waterloo - Sunnyside Home
- Construction start
- Jul 4, 2023(actual)
- Construction end
- Dec 4, 2023(actual)
Against the original forecast
- Construction start14 months lateforecast May 2, 2022
- Construction end11 months lateforecast Dec 30, 2022
Also in Kitchener
- Stormwater Network Adaptation$50.0M
- Aquatic Centre RBJ Schlegel Park$9.8M
- Installing mechanical ventilation in buildings where none currently exist; Window repair or replacement for fresh air intake$7.9M
- HVAC Upgrades; Upgrading wireless access points; Window replacement; Washroom upgrades; Installing cooling / air conditioning units; room partition replacement$7.6M
- Kitchener Public Library Southwest Community Library$6.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59490 in the federal list. How to read these figures.