Back to projects

Replace Ventilation Unit #3

Toronto, Ontario

completeVentilationCVRIS
Federal contribution
$345,200
Federal share80%

of $431.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
202220232024
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 1, 2022(actual)
Construction end
Mar 31, 2024(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2022
  • Construction end9 months earlyforecast Dec 31, 2024

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59502 in the federal list. How to read these figures.