Back to projects

HVAC System Replacement and Upgrades

Toronto, Ontario

completeVentilationCVRIS
Federal contribution
$220,480
Federal share80%

of $275.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
2022
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 1, 2021(actual)
Construction end
Aug 5, 2022(actual)

Against the original forecast

  • Construction start6 months lateforecast May 3, 2021
  • Construction end7 months lateforecast Dec 31, 2021

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59506 in the federal list. How to read these figures.