HVAC Upgrades - Seven Oaks
Federal contribution
$240,000
Federal share80%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
20222023
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Toronto - Seven Oaks
- Construction start
- May 25, 2022(actual)
- Construction end
- Aug 14, 2023(actual)
Against the original forecast
- Construction start7 weeks lateforecast Apr 4, 2022
- Construction end5 months earlyforecast Dec 31, 2023
Also in Toronto