CARS - irrigation system
Federal contribution
$383,502
Federal share80%
of $479.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
20222023
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre d'Accueil Roger Seguin - Centre d'Accueil Roger Seguin
- Construction start
- Feb 14, 2022(actual)
- Construction end
- Sep 30, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Dec 15, 2021
- Construction end18 months lateforecast Mar 31, 2022
Also in Clarence-Rockland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59532 in the federal list. How to read these figures.