Watermain Looping Completion for Village of Clarence-Creek
Federal contribution
$170,470
Federal share15%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
20182019
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of Clarence-Rockland
- Construction start
- May 15, 2017(actual)
- Construction end
- Dec 21, 2018(actual)
Against the original forecast
- Construction start7 months earlyforecast Dec 1, 2017
Also in Clarence-Rockland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49359 in the federal list. How to read these figures.