Watermain Looping Completion for Village of Clarence-Creek

Clarence-Rockland, Ontario

completeDrinking WaterCWWF
Federal contribution
$170,470
Federal share15%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
May 15, 2017(actual)
Construction end
Dec 21, 2018(actual)

Against the original forecast

  • Construction start7 months earlyforecast Dec 1, 2017