Boundary Road Pedestrian Path Construction
Federal contribution
$132,968
Federal share80%
of $166.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Pembroke
- Construction start
- Oct 18, 2021(actual)
- Construction end
- Nov 28, 2022(actual)
Against the original forecast
- Construction start2 weeks lateforecast Oct 1, 2021
Also in Pembroke
- HVAC System UV Treatment; HVAC Duct Sealing; Ventilation$2.2M
- Reconstruction of a Section of Pembroke Street West$2.0M
- Bennet Street and Boundary Road Watermain Replacement and Taylor Bridge Watermain Suspension$1.9M
- HVAC Upgrades; Portable Replacement; Installation of Bottle Filling Stations$1.5M
- Algonquin Trail North Active Transportation Enhancements$1.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59561 in the federal list. How to read these figures.