Replacement of the 1986 Tanker Truck-Grey Firehall

Huron East, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$90,334
Federal share80%

of $112.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Municipality of Huron East
Construction start
Sep 21, 2021(actual)
Construction end
Jun 8, 2023(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Oct 18, 2021
  • Construction end5 months lateforecast Dec 30, 2022

Also in Huron East

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59583 in the federal list. How to read these figures.