Rehabilitation of Bayfield Street Shoreline Protection
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Municipality of Meaford
- Construction start
- Aug 30, 2021(actual)
- Construction end
- Sep 30, 2021(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 15, 2021
- Construction end2 weeks lateforecast Sep 15, 2021
Also in Meaford
- Grandview Drive & Susan Street Reconstruction / Development of Alternate Water Distribution Trunk Main$909.5K
- Replacement of Structure 043$736.0K
- Replacement of Lakeshore Road and Algonquin Drive Watermains$729.3K
- Construction of St. Vincent Street Water Booster Station$562.0K
- Replacement of the Harris Bridge$338.4K