Rehabilitation of Bayfield Street Shoreline Protection

Meaford, Ontario

completeDisaster MitigationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Municipality of Meaford
Construction start
Aug 30, 2021(actual)
Construction end
Sep 30, 2021(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jul 15, 2021
  • Construction end2 weeks lateforecast Sep 15, 2021