Morrisburg Pathway Rehabilitation
Federal contribution
$115,830
Federal share80%
of $144.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Corporation of the Municipality of South Dundas
- Construction start
- Oct 4, 2021(actual)
- Construction end
- Jun 10, 2022(actual)
Against the original forecast
- Construction start5 months lateforecast May 3, 2021
- Construction end3 weeks earlyforecast Jun 30, 2022
Also in South Dundas
- Iroquois Wastewater Treatment Plant Upgrade (South Dundas)$9.0M
- Carmen Road Watermain Rehabilitation$896.2K
- Water Tower Replacement serving the villages of Morrisburg and Iroquois approximately 2,200 households$227.6K
- Ontario Street Reconstruction of Water main & Sanitary$180.0K
- Cathode Study and Replacement$37.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59596 in the federal list. How to read these figures.