Morrisburg Pathway Rehabilitation

South Dundas, Ontario

completeActive TransportationCVRIS
Federal contribution
$115,830
Federal share80%

of $144.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 4, 2021(actual)
Construction end
Jun 10, 2022(actual)

Against the original forecast

  • Construction start5 months lateforecast May 3, 2021
  • Construction end3 weeks earlyforecast Jun 30, 2022

Also in South Dundas

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59596 in the federal list. How to read these figures.