Ontario Street Reconstruction of Water main & Sanitary

South Dundas, Ontario

completeDrinking WaterCWWF
Federal contribution
$180,000
Federal share24%

of $750.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2018
20192020
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Feb 14, 2019(actual)
Construction end
Oct 31, 2020(actual)

Against the original forecast

  • Construction start8 months lateforecast Jun 1, 2018
  • Construction end5 months earlyforecast Mar 31, 2021

Also in South Dundas

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52140 in the federal list. How to read these figures.