Emergency Vehicles Pandemic Response
Federal contribution
$93,760
Federal share80%
of $117.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- County of Oxford
- Construction start
- Apr 16, 2021(actual)
- Construction end
- Mar 16, 2022(actual)
Against the original forecast
- Construction start2 weeks lateforecast Apr 1, 2021
- Construction end2 months lateforecast Dec 31, 2021
Also in Woodstock
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59598 in the federal list. How to read these figures.