CP Rail Trail Stone Dusting/Cycling & Trails Signs
Federal contribution
$201,181
Federal share80%
of $251.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
202220232024
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- County of Grey
- Construction start
- Sep 26, 2022(actual)
- Construction end
- Dec 29, 2023(actual)