Grey Road 30 Stormwater Management Study
Federal contribution
$14,898
Federal share50%
of $30.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 16, 2017
ApprovedFeb 26, 2018
2018
Built
Approved 8 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- County of Grey
- Construction start
- Aug 9, 2017(actual)
- Construction end
- Jun 30, 2018(actual)
Against the original forecast
- Construction start6 months lateforecast Jan 30, 2017
Also in Grey