Tree Planting Initiative
Federal contribution
$118,000
Federal share80%
of $147.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- The Corporation of The City of Guelph
- Construction start
- Jan 5, 2022(actual)
- Construction end
- Oct 13, 2022(actual)
Against the original forecast
- Construction start3 months earlyforecast Apr 11, 2022
- Construction end14 months earlyforecast Nov 30, 2023
Also in Guelph
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59621 in the federal list. How to read these figures.