Back to projects

Town of Watson - Arena Renovations

Watson, Saskatchewan

completeRecreationCVRIS
Federal contribution
$107,057
Federal share40%

of $267.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 6, 2021
2022
Built

Approved 7 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Watson
Construction start
Jan 31, 2022(actual)
Construction end
Sep 30, 2022(actual)

Also in Watson

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59633 in the federal list. How to read these figures.