Back to projects

Sewage Pumping Station and Force Main Upgrade

Watson, Saskatchewan

completeWastewaterCWWF
Federal contribution
$1.1M
$1,094,500
Federal share50%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 11, 2017
2017201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Watson
Construction start
Jun 1, 2017(actual)
Construction end
Jun 30, 2020(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2017
  • Construction end3 months earlyforecast Sep 30, 2020