Meewasin Valley Authority - Meewasin Trail Enhancements
Federal contribution
$2.7M
$2,719,614
Federal share40%
of $6.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
today
202220232024202520262027
BuiltForecast
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Meewasin Valley Authority
- Construction start
- Aug 9, 2021(actual)
- Construction end
- Dec 31, 2026(forecast)
Also in Saskatoon