Back to projects

Meewasin Valley Authority - Meewasin Trail Enhancements

Saskatoon, Saskatchewan

underwayActive TransportationCVRIS
Federal contribution
$2.7M
$2,719,614
Federal share40%

of $6.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
today
202220232024202520262027
BuiltForecast
Program
COVID-19 Resilience Stream
Ultimate recipient
Meewasin Valley Authority
Construction start
Aug 9, 2021(actual)
Construction end
Dec 31, 2026(forecast)

Also in Saskatoon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59639 in the federal list. How to read these figures.