HVAC Upgrade and Air Cooled Chiller Replacement

Toronto, Ontario

completeVentilationCVRIS
Federal contribution
$856,000
Federal share80%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
20222023
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 1, 2021(actual)
Construction end
Sep 30, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 1, 2021
  • Construction end8 months lateforecast Jan 31, 2023