HVAC (Air Conditioning, Air Handling Unit, Fans) Upgrade
Federal contribution
$5.4M
$5,372,514
Federal share80%
of $6.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
202220232024
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- The Jewish Home for the Aged - The Jewish Home for the Aged
- Construction start
- Jul 31, 2021(actual)
- Construction end
- Apr 30, 2024(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2021
- Construction end23 months earlyforecast Mar 31, 2026
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59646 in the federal list. How to read these figures.