Humidifier Replacement and HVAC Filtration Upgrade

Manitouwadge, Ontario

completeVentilationCVRIS
Federal contribution
$236,049
Federal share80%

of $295.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
202220232024
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 1, 2021(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start6 months lateforecast May 10, 2021
  • Construction end2.3 years lateforecast Sep 1, 2021

Also in Manitouwadge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59647 in the federal list. How to read these figures.