Manitouwadge Rec Centre - Ventilation Upgrades
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
today
20222023202420252026
BuiltForecast
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Manitouwadge
- Construction start
- Feb 15, 2026(actual)
- Construction end
- Oct 1, 2026(forecast)
Against the original forecast
- Construction start3.5 years lateforecast Sep 1, 2022
Also in Manitouwadge