Replacement of the drinking water system and upgrading of a crawl space
Federal contribution
$818,720
Federal share80%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Montréal (CSSDM)
- Construction start
- Feb 21, 2023(actual)
- Construction end
- Nov 21, 2023(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Mar 20, 2023
- Construction end3 months lateforecast Aug 31, 2023
Also in Montréal