Replacement of fire alarm and intercommunication systems
Federal contribution
$344,000
Federal share80%
of $430.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Montréal (CSSDM)
- Construction start
- Apr 13, 2022(actual)
- Construction end
- Sep 20, 2023(actual)
Against the original forecast
- Construction start8 weeks lateforecast Feb 17, 2022
- Construction end11 months lateforecast Oct 31, 2022