Renovation of sanitary blocks (Phase 1)

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$653,600
Federal share80%

of $817.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 5, 2022(actual)
Construction end
Nov 1, 2022(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Feb 7, 2022
  • Construction end4 months earlyforecast Mar 7, 2023

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59685 in the federal list. How to read these figures.