Roof replacement

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$860,000
Federal share80%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 25, 2021(actual)
Construction end
Feb 7, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 15, 2021
  • Construction end2 months lateforecast Nov 30, 2021

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59686 in the federal list. How to read these figures.