Replacement of exterior doors

Bois-des-Filion, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$229,711
Federal share80%

of $287.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 26, 2021(actual)
Construction end
Jan 17, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 15, 2021
  • Construction end5 weeks lateforecast Dec 15, 2021