Roof replacement
Federal contribution
$1.3M
$1,302,183
Federal share80%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de service scolaire de la Seigneurie-des-Mille-Îles
- Construction start
- Jun 28, 2021(actual)
- Construction end
- Mar 18, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 15, 2021
- Construction end3 months lateforecast Dec 15, 2021
Also in Bois-des-Filion