Renovation of the outer casing
Federal contribution
$1.4M
$1,441,787
Federal share76%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Montréal (CSSDM)
- Construction start
- Mar 22, 2021(actual)
- Construction end
- Nov 23, 2022(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Apr 15, 2021
- Construction end4 weeks lateforecast Oct 27, 2022
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59700 in the federal list. How to read these figures.