Paving Trails at Lakeside Park

Kingsville, Ontario

completeActive TransportationCVRIS
Federal contribution
$92,291
Federal share80%

of $115.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Kingsville
Construction start
Sep 20, 2021(actual)
Construction end
Jan 31, 2022(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Dec 31, 2021

Also in Kingsville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59712 in the federal list. How to read these figures.