Safety and Distancing Retrofits for Sydenham Office
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
2022
Built
Approved 3 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of South Frontenac
- Construction start
- Jul 4, 2022(actual)
- Construction end
- Oct 17, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 25, 2022
- Construction end2 months earlyforecast Dec 31, 2022