Enabling Accessibility at Senior and Youth Centre
Federal contribution
$102,898
Federal share80%
of $128.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2021
2022
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Corporation of the Township of Uxbridge
- Construction start
- Jul 28, 2021(actual)
- Construction end
- Jan 25, 2022(actual)
Against the original forecast
- Construction end4 weeks lateforecast Dec 31, 2021
Also in Uxbridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59742 in the federal list. How to read these figures.