Southgate Council Chambers Relocation and Upgrades

Southgate, Ontario

completeVentilationCVRIS
Federal contribution
$79,200
Federal share80%

of $99.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Southgate
Construction start
Sep 7, 2021(actual)
Construction end
Oct 1, 2022(actual)