Southgate Council Chambers Relocation and Upgrades
Federal contribution
$79,200
Federal share80%
of $99.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Southgate
- Construction start
- Sep 7, 2021(actual)
- Construction end
- Oct 1, 2022(actual)
Also in Southgate