New Construction of Dundalk Drinking Water Production Well and Pumphouse D5 250 Hahen Street East
Federal contribution
$50,000
Federal share3%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2017
201720182019
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Southgate
- Construction start
- Aug 1, 2016(actual)
- Construction end
- Oct 31, 2019(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2016
Also in Southgate
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50232 in the federal list. How to read these figures.