Providence Bay Boardwalk East End Upgrade

Central Manitoulin, Ontario

completeActive TransportationCVRIS
Federal contribution
$79,200
Federal share80%

of $99.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 1, 2022(actual)
Construction end
Dec 16, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast Mar 31, 2022
  • Construction end2 weeks earlyforecast Dec 31, 2022