Providence Bay Boardwalk East End Upgrade
Federal contribution
$79,200
Federal share80%
of $99.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
20222023
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Central Manitoulin
- Construction start
- Aug 1, 2022(actual)
- Construction end
- Dec 16, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Mar 31, 2022
- Construction end2 weeks earlyforecast Dec 31, 2022
Also in Central Manitoulin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59752 in the federal list. How to read these figures.