Replacement of the Programmable Logic Controller at the Mindemoya Water Treatment Plant
Federal contribution
$89,063
Federal share41%
of $215.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 17, 2017
20182019
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Central Manitoulin
- Construction start
- Nov 1, 2018(actual)
- Construction end
- Jan 22, 2019(actual)
Against the original forecast
- Construction start18 months lateforecast May 1, 2017
- Construction end14 months lateforecast Nov 30, 2017
Also in Central Manitoulin