Back to projects

Hastings Manor Long Term Care (LTC) Flooring

Belleville, Ontario

completeHealthcare InfrastructureCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
County of Hastings
Construction start
Jul 5, 2021(actual)
Construction end
Nov 2, 2021(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 20, 2021