Back to projects

Community Park Multi-Use Path

South Stormont, Ontario

completeActive TransportationCVRIS
Federal contribution
$79,999
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of South Stormont
Construction start
Sep 1, 2021(actual)
Construction end
Oct 26, 2021(actual)

Also in South Stormont

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59770 in the federal list. How to read these figures.