Community Park Multi-Use Path
Federal contribution
$79,999
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of South Stormont
- Construction start
- Sep 1, 2021(actual)
- Construction end
- Oct 26, 2021(actual)
Also in South Stormont
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59770 in the federal list. How to read these figures.