HVAC Air Circulation Equipment Upgrade

Collingwood, Ontario

completeVentilationCVRIS
Federal contribution
$112,025
Federal share80%

of $140.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
2022
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 16, 2021(actual)
Construction end
Oct 28, 2022(actual)

Against the original forecast

  • Construction end2 months earlyforecast Dec 31, 2022