Renovations for Social Distancing and Safety

Essex, Ontario

completeOtherCVRIS
Federal contribution
$280,331
Federal share80%

of $350.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Essex
Construction start
May 14, 2021(actual)
Construction end
Sep 6, 2022(actual)

Against the original forecast

  • Construction end3 months lateforecast May 31, 2022

Also in Essex

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59784 in the federal list. How to read these figures.