Renovation project of the schoolyard pavement and exterior staircases and the storm drainage network
Federal contribution
$1.2M
$1,162,864
Federal share70%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Montréal (CSSDM)
- Construction start
- Jun 25, 2021(actual)
- Construction end
- Aug 23, 2021(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 1, 2021