Boiler room upgrade and replacement of the storm and sanitary drainage network
Federal contribution
$1.3M
$1,341,600
Federal share80%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Montréal (CSSDM)
- Construction start
- Aug 30, 2021(actual)
- Construction end
- Aug 28, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2021
- Construction end8 months lateforecast Dec 23, 2022
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59816 in the federal list. How to read these figures.