Upgrade of the boiler room and replacement of the storm and sanitary drainage network
Federal contribution
$894,400
Federal share80%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
202220232024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Montréal (CSSDM)
- Construction start
- Jun 14, 2021(actual)
- Construction end
- Dec 15, 2023(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2021
- Construction end12 months lateforecast Dec 23, 2022
Also in Montréal